Update on Carnarvon Jetty
Time for a bit of an update on Carnarvon jetty repairs.The work barge/pontoon has been commissioned and work has started on replacing the burnt out section.They have had a few loads of timber arrive from down south as well as some unwanted power poles from Lake McLeod salt mines with compliments from Rio Tinto.
They expect it will take approximately 4 months to fill the missing section of the jetty.
There will be quite a bit of work to be done at the outer end due to the workers not being able to gain access to it,how long this will take is unknown at this time.As soon as I hear something you will be the first to know.
The train is still doing its run out as far as the missing section,if you are in town please take the run out or make a donation because the funds are still needed
Colin Hay
Posts: 10407
Date Joined: 23/10/07
Thanks a lot carnarvonite
I know quite a few members love fishing at the Carnarvon Jetty (me included) and it is good to know things are starting to move along.
Moderator. Proud member of the Fishwrecked "Old Farts". Make sure your subscribed to Fishwrecked Reeltime http://fishwrecked-reeltime.com/
Dreamweaver
Posts: 4688
Date Joined: 01/12/07
That's Grate News John
Nice to see commencement on such a pivotal icon. Well worth the donations for sure!
Soon to be de "dreamweaver" ed!
joe amato
Posts: 731
Date Joined: 21/12/08
thats gr8 news
finally the mulloway capital of western australia is getting a facelift,best news i have heard in ages,havent been there in ages,but thinking about going there in the near future.
nev
Posts: 193
Date Joined: 04/02/09
Carnarvon Jetty Repairs
Who are doing all the repairs John ? Be good to see it up and running again.........
carnarvonite
Posts: 8664
Date Joined: 24/07/07
Labour
They have hired 4 men,two to work from the pontoon and two up top.They use the train to haul the timber out from their shed onshore.